Live calcs GEN-1 · 150 kW standby — 188 kVA · 226 A FLA
Connected 150 kVA · demand 120 kVA · loading 64%
Generator loading 64% of 188 kVA rating (NEC 702.4(B))
Fuel ~9.6 gal/h (generic curve) · ~28.7 h/tank · ~230 gal/day
GEN-1 → ATS-1 feeder
80 ft · 300 Cu · 226 A @ 480 V 3φ
Voltage drop 0.4% is within the 3% guidance (NEC 210.19(A) IN)
Conduit fill 19% (limit 40%) (NEC Ch.9 T.1)
Load 226 A within adjusted ampacity 285 A (NEC 310.16)
Trench route — burial depth, cover, and raceway type for the wiring method must be verified by a licensed EC. (NEC 300.5)
ATS-1 → MDP
40 ft · 300 Cu · 226 A @ 480 V 3φ
Voltage drop 0.2% is within the 3% guidance (NEC 210.19(A) IN)
Conduit fill 16% (limit 40%) (NEC Ch.9 T.1)
Load 226 A within adjusted ampacity 285 A (NEC 310.16)
Unverified planning aid. Verify against official NEC, local code, AHJ, and qualified professional review before real-world use.
What you're looking at
A 150 kW commercial standby generator install — smaller commercial building, new installation, pad-mounted unit on an exterior slab. This demo shows the planning layer a PM builds before mobilizing.
The site plan includes: generator pad placement, ATS location, feeder route in trench, interior EMT run from ATS to the main service, crane path and staging zone, and overhead line clearances.
Planning checks run on every conduit and feeder segment: voltage drop (planning estimate — verify with EOR), conduit fill (NEC Art. 358/362 placeholder — not a compliance determination), and ampacity flag. Each check is a planning prompt , not an engineering output.
Planning packet would include:
• Scope summary + open clarifying questions • Feeder, conduit, and ATS coordination notes • Generator sizing + fuel/runtime planning estimate • Grounding and bonding checklist (licensed electrician must verify) • Material planning list with IFC drawing references • Permit / AHJ / inspection reminders • Crew task sequence and LOTO reminders Static demo — fictional sample location and data. Nothing uploaded or saved. Ask about a Founding Job Packet to plan your own job.