350 kW generator replacement — planned scope-first.
A planning assistant for contractors and project managers. It turns a contract, the engineer of record's issued-for-construction drawings, field measurements, specs, photos, and notes into a clarified scope, a sequenced work plan with manpower and duration, an editable material list, and a crew packet. It consumesthe engineer's drawings — it does not produce engineering.
Goal: turn a messy 2–3 hour planning pass into a 20-minute draft plus human review. A target, not a guarantee — real job complexity and site conditions vary.
The job (sample — fictional)
Replace an existing 350 kW emergency standby generator with a new 350 kW unit. The new unit is physically larger. Remove the old generator, transport it to the customer's yard, and unload it in place — a heavy-lift / rigging job.
Scope summary
Replace a 350 kW emergency standby generator with a new 350 kW unit (larger footprint). Disconnect and demo the existing unit, rig it out, transport it to the customer's yard, and set it in place. Set the new unit on the existing pad and reconnect power, control, and fuel per the engineer of record's issued-for-construction drawings.
Source-of-truth order
- 1. Contract / scope of work — What is actually owed — inclusions and exclusions.
- 2. Issued-for-construction (IFC) drawings — The controlling design from the engineer of record.
- 3. Measurements / site conditions — Real field reality on the ground.
- 4. Specs / manuals — Manufacturer and installation requirements.
- 5. Photos — Supporting context.
- 6. Notes — Your annotations — lowest authority; never overrides the above.
Clarifying questions (asked before generating anything)
The contract input here is thin, so the assistant asks first instead of guessing. It will not produce a work plan or material list until the answers that drive scope are known.
- Q1Are the issued-for-construction electrical drawings and the new generator submittal / cut sheet available? (They control clearances, conduit, and conductor sizing.)
- Q2What are the new unit's footprint and weight versus the existing pad? Does the existing pad and anchor pattern accept the larger unit, or is pad modification in scope?
- Q3Is the rigging path confirmed — crane position, swing radius, ground bearing, overhead lines or obstructions?
- Q4Fuel system: is the existing day-tank / fuel piping reused or replaced, and who disconnects and purges it?
- Q5Is transport to the customer yard in scope, and who provides the receiving location and offload equipment there?
- Q6Who owns permits and AHJ inspection — this contract or others?
- Q7What outage window is allowed, and is temporary power needed during the swap?
Inclusions, exclusions, and change-order risk (internal view)
This is the contractor/PM (internal) view. The customer view never says "change order" — it uses calm language. See the job-coordination demo.
Included
- • Lockout/tagout and disconnect of power, control, and fuel per the IFC drawings.
- • Demo and rig-out of the existing 350 kW unit.
- • Load and transport the old unit to the customer's yard.
- • Offload and set the old unit in place at the yard.
- • Set the new 350 kW unit on the verified pad.
- • Reconnect power, control, and fuel per the IFC drawings.
- • Functional test and commissioning support.
Excluded / unknown
- • Pad / anchor modification for the larger footprint (pending measurements).
- • New fuel piping or day-tank (pending fuel-system answer).
- • Temporary power during the outage (pending outage window).
- • Permit and AHJ fees (pending responsibility answer).
- • Structural review of the rigging path (by others).
- • Abatement or unforeseen / concealed site conditions.
Change-order risk (internal)
- • Existing pad or anchor pattern does not fit the larger unit → pad rework.
- • Concealed conditions found during demo.
- • Rigging path needs road plates, ground protection, or a utility de-energization.
- • Existing fuel system is not reusable.
- • Required outage window exceeds the plan.
Work plan — manpower & duration
Planning estimate only — not a guarantee. Confirm with the crew, the engineer of record, and site conditions.
Gate before mobilization
Requires confirmed outage window
Rigging path confirmed; weather-dependent
Permitted transport if oversize
Receiving location + equipment confirmed
Pad fit = change-order risk
Conductors / conduit per drawings
Manufacturer startup by others if required
| # | Task | Crew role | Est. duration | Dependency / notes |
|---|---|---|---|---|
| 1 | Pre-job: confirm IFC drawings, submittal, rigging plan, outage window | PM / coordinator | 0.5–1 day | Gate before mobilization |
| 2 | Site prep + LOTO; disconnect feeders, control, fuel | Electrician (2) | 0.5 day | Requires confirmed outage window |
| 3 | Rig out existing 350 kW unit (crane + rigging) | Rigging crew + crane op (3–4) | 0.5–1 day | Rigging path confirmed; weather-dependent |
| 4 | Load + transport old unit to customer yard | Driver + rigger (2) | 0.5 day | Permitted transport if oversize |
| 5 | Offload + set old unit in place at yard | Rigging crew (3) | 0.25–0.5 day | Receiving location + equipment confirmed |
| 6 | Verify / modify pad; set new (larger) unit | Rigging + electrician (3–4) | 0.5–1 day | Pad fit = change-order risk |
| 7 | Reconnect power, control, fuel per IFC | Electrician (2–3) | 1–1.5 days | Conductors / conduit per drawings |
| 8 | Functional test + commissioning support | Electrician + commissioning (2) | 0.5 day | Manufacturer startup by others if required |
Rough total: ~4–6 crew-days (planning estimate; depends on pad fit, rigging path, and outage window).
Material planning list — draft (illustrative placeholders)
Illustrative planning placeholders — not a purchase list or engineering BOM. Confirm all quantities, sizes, and specs against the IFC drawings and submittal before ordering. Edits are not saved in this static demo.
| Item / description | Qty | Unit |
|---|---|---|
| Generator / pad / anchoring (planning) | ||
| Rigging / access (planning — confirm SWL and path before mobilizing) | ||
| Conduit / feeders (planning — size and type per IFC drawings) | ||
| ATS / gear coordination (planning) | ||
| Grounding / bonding (planning — verify with EOR and AHJ) | ||
| Fuel coordination (planning — confirm scope with EOR) | ||
| Outage / safety / temporary power (planning) | ||
| Permit / AHJ / inspection coordination (planning) | ||
One-page packet preview
This is what a completed field packet looks like — a printable, one-page summary a PM can hand to the crew. Use your browser's Print / Save as PDF to export it.
Munda Field Planner — Planning Packet · Demo / Fictional Data
350 kW Generator Replacement
Planning aid only — not engineering, code, permit approval, or a final quote. Verify with licensed contractor, engineer of record, AHJ, and manufacturer.
Scope snapshot
Replace a 350 kW standby generator (new unit is larger). Rig out the old unit, transport to customer's yard, set the new unit on the existing pad, reconnect power / control / fuel per IFC drawings. 4–6 crew-days estimated.
Open questions before mobilizing
- ?IFC drawings + submittal confirmed available?
- ?Pad accepts the larger footprint / anchor pattern?
- ?Rigging path, crane position, and ground bearing confirmed?
- ?Fuel system: reuse or replace? Who purges it?
- ?Permit and AHJ responsibility confirmed?
- ?Outage window duration and temp-power requirement?
Internal PM — watch list (not shown to customer)
- !Pad doesn't fit larger unit → pad rework change order
- !Concealed conditions during demo
- !Rigging path needs road plates or utility clearances
- !Fuel system not reusable
- !Outage window shorter than needed
Crew sequence (planning estimate)
- 1.Pre-job: confirm IFC drawings, submittal, rigging plan, outage window — PM / coordinator, est. 0.5–1 day
- 2.Site prep + LOTO; disconnect feeders, control, fuel — Electrician (2), est. 0.5 day
- 3.Rig out existing 350 kW unit (crane + rigging) — Rigging crew + crane op (3–4), est. 0.5–1 day
- 4.Load + transport old unit to customer yard — Driver + rigger (2), est. 0.5 day
- 5.Offload + set old unit in place at yard — Rigging crew (3), est. 0.25–0.5 day
- 6.Verify / modify pad; set new (larger) unit — Rigging + electrician (3–4), est. 0.5–1 day
- 7.Reconnect power, control, fuel per IFC — Electrician (2–3), est. 1–1.5 days
- 8.Functional test + commissioning support — Electrician + commissioning (2), est. 0.5 day
Material planning categories (illustrative — see full list above)
Quantities and specs TBD — confirm against IFC drawings and submittal. Not a purchase list or engineering BOM.
Customer-safe summary (calm wording for the owner)
We're replacing your standby generator with the new unit and moving the old one to your yard. We'll confirm the details — pad fit, crane path, and outage window — before we mobilize and will let you know if anything may affect price or schedule before doing extra work.
Internal risks and change-order language stay internal. The customer sees "may affect price or schedule" and "needs your approval" — not "change order."
Browser print only — no uploads, no data sent.
This is not engineering work. Outputs are planning aids based on user-provided contract, drawings, measurements, and qualified professional inputs. Verify all work with the contractor, engineer of record, AHJ, manufacturer instructions, and applicable requirements before real-world use. Uploads are a future, invite-only private-pilot capability — currently OFF. This demo is browser-only and deterministic — nothing is uploaded or saved.