Internal PM review: approval-needed items
Transfer switch needs replacement (found on site)
Needs approvalImpact: May add about half a day; materials cost varies
Customer-safe: We found the transfer switch should be replaced. This may affect price or schedule — we'll confirm before doing it.
Fuel line length longer than expected
Needs approvalImpact: May add minor materials; schedule likely unchanged
Customer-safe: The fuel run is a bit longer than planned. A small materials adjustment may apply; we'll confirm with you.
Tracking only — no e-signature, no contract, no payment. Final pricing/approval happen off-app.
Materials readiness
Daily field report
Completed today
- ✓ Set + leveled the pad
- ✓ Staged conductors
Blocked
- ⛔ ATS condition unconfirmed — pending site verify
Materials needed
- • Fuel fittings
- • Confirm ATS model
Next step
Confirm transfer switch, then set the generator
Customer-safe summary: Crew made progress on prep today. One item is being confirmed; we'll update you before the next step.
Job costing (rough)
Materials: Most materials ready; 1 long-lead + 1 missing item to confirm
Preview only — a rough planning indicator, NOT accounting and NOT a final quote.